AFUR logo AFURAFUR Renewable Energy Platform
← Dashboard

Saved preliminary assessment

AFUR Pilot Project

Zimbabwe · Mini grid · Assessed 14 Jul 2026

Screened
Recommended PV size261.5kWp
Total CAPEX$291,736USD
Simple payback4.57years
Readiness0%evidence complete

Energy impact

Annual performance

Annual generation420,000 kWh
Year 1 net savings$63,866
CO2 avoided273.0 tonnes

Project pathway

Recommended next action

Resolve the first outstanding readiness item before formal utility engagement:

Identify the network utility or system operator responsible for the connection.

Solar PV

Technical screening

261.5 kWprecommended capacity
Monthly consumption
50,000 kWh
Peak sun hours
5.50/day
Solar coverage
70.00%
Performance ratio
80%
Annual degradation
0.50%

Battery

Resilience screening

154.3 kWhnominal storage
Critical load
27.8 kW
Usable capacity
111.1 kWh
Backup duration
4.00 hours
Critical-load coverage
40.00%
Technical boundary

Validate the load profile, site conditions, structural capacity, equipment selection and protection design before detailed engineering.

Solar CAPEX$222,291USD
Battery CAPEX$69,444USD
20-year NPV$462,225USD
Annual O&M$3,334USD/year

Investment structure

CAPEX breakdown

Solar PV 76%Battery 24%

Evidence trail

Financial assumptions

Electricity tariff
$0.1600/kWh
Tariff escalation
5.00%
Discount rate
10.00%
Analysis period
20 years
Solar installed cost
$850/kWp

Readiness score

Grid and sanctioning evidence

0%
0 of 6 evidence items available
Operating mode
Self consumption

Action register

Before formal engagement

  1. 1

    Identify the network utility or system operator responsible for the connection.

  2. 2

    Document site ownership, lease rights or formal authority to use the site.

  3. 3

    Obtain interval load data to validate demand, export and battery assumptions.

  4. 4

    Prepare a preliminary electrical single-line diagram.

  5. 5

    Define the metering, anti-islanding and protection approach.

  6. 6

    Complete an initial environmental and social screening.

Regulatory boundary

This is a general readiness screen. Confirm licensing thresholds, grid codes, tariffs, approvals and application procedures with the relevant authority in Zimbabwe.